Scheduling in business days¶
Chain project tasks so each starts after the previous one finishes —
skipping weekends and holidays with WORKDAY.INTL.
You'll need: abax only.
Run it¶
What you should see¶
Design ( 5d) finishes 2026-09-09
Build (10d) finishes 2026-09-23
Test ( 4d) finishes 2026-09-29
Ship ( 1d) finishes 2026-09-30
Whole project: 21.0 working days
How it works¶
- Dates in abax are ISO strings (
"2026-09-01") — no serial-number arithmetic to learn. - Each task's finish is
=WORKDAY.INTL(previous_finish, days, 1, D1:D2): weekend spec1means Saturday+Sunday off, andD1:D2holds the holidays (Labor Day and Thanksgiving here — note the Design task takes 5 working days but lands 8 calendar days out). =NETWORKDAYS.INTL(start, end, 1, D1:D2)counts the working days in the whole span — 21, not the 30 calendar days.- Other weekend specs handle Fri/Sat weekends, single days off, or a
custom
"0000011"mask — see the formula reference.