Project management: task tracking

Track a project on an ordinary sheet: build a task list, run critical-path scheduling, and export a status report — then explore the ten PM views in the GUI (Kanban, Card, Calendar, Gantt, Timeline, Dashboard, Roadmap, Resources, Budget, OKRs) plus import/export and scenario analysis.

You'll need: nothing beyond abax for run.py (pure stdlib); a Qt binding (pip install "abax[all]") for the GUI walkthrough below it.

Run it

cd docs/examples/project-management/task-tracking
python run.py

What you should see

5 tasks scheduled; critical path:
  T1 (Design) -> T2 (Build core) -> T4 (Integrate) -> T5 (Ship)

slack per task (days):
  T1  slack=0  <- critical
  T2  slack=0  <- critical
  T3  slack=2
  T4  slack=0  <- critical
  T5  slack=0  <- critical

wrote out/status.md, out/gantt.svg, out/sprint.abax
open the workbook in the GUI (Project menu lights up):
  abax out/sprint.abax

How it works

  • The task sheet is typed exactly the way you would in the grid; headers are matched by alias (Due/End/Finish all work, Assignee/Owner/Who all work).
  • Project(...) + wb.projects.add(...) registers the sheet region — the same thing Project > New project from sheet… does in the GUI.
  • parse_tasks reads the region back as Task objects; compute_cpm runs the forward/backward critical-path pass and critical_path extracts the zero-slack chain (T3, the parallel UI track, has 2 days of slack).
  • report_markdown renders the roll-up (progress, health, overdue, milestones) and export_gantt_svg draws the chart — both plain files you can commit, mail, or publish.
  • The saved out/sprint.abax carries the project registration, so opening it in the GUI lights up the Project menu with everything below already wired.

The rest of this page is a GUI walkthrough of the same features.

Set up a task sheet

  1. Open abax (abax gui) and create a sheet with these headers in row 1:

    Title | Status | Start | Due | Assignee | Effort | Cost

  2. Add a few tasks in the rows below:

    Design UI | To Do | 2026-08-01 | 2026-08-15 | Alice | 40 | 5000 Build backend | In Progress | 2026-08-05 | 2026-09-01 | Bob | 80 | 8000 Write tests | To Do | 2026-09-01 | 2026-09-15 | Alice | 20 | 2000 Deploy | To Do | 2026-09-15 | 2026-09-20 | Bob | 10 | 1000

Register a project

  1. Project > New project from sheet... (or type "Project: new" in the command palette with Ctrl+Shift+P).
  2. Name the project, confirm the auto-detected columns, and click OK.

Explore the views

  1. Project > Open project views opens the dockable PM panel with ten tabs:
  2. Kanban — drag cards between status columns.
  3. Card — responsive grid with sort/filter.
  4. Calendar — month grid with drag-to-reschedule.
  5. Gantt — draggable bars, dependency arrows, critical-path highlight.
  6. Timeline — swim lanes by assignee.
  7. Dashboard — KPI tiles, health table, milestones.
  8. Roadmap — multi-project timeline with cross-project links.
  9. Resources — people x weeks workload heatmap.
  10. Budget — budget-vs-actual bars, EVM KPI tiles.
  11. OKRs — objectives and key results.

Import tasks from CSV or MS Project

  1. Project > Import tasks... — open a CSV file (auto-detects delimiter and header names) or an MS Project XML export. The parsed tasks are appended to the active project's sheet (matched to your columns by header name) as a single undo step.

Export a Gantt chart

  1. Project > Export Gantt SVG... — saves the Gantt chart as an SVG file with a colour-key legend.

What-if scenarios

  1. Project > Scenarios... — the scenario editor lets you override task fields (dates, effort, cost, assignee, status) without touching the sheet. Click Apply to Sheet to commit the overrides as a single undo step.

Export a status report

  1. Project > Export report... — generates a status report with per-project tables, task summaries, and milestones. The file dialog offers both HTML and Markdown formats — save with a .md extension for Markdown output.

From the CLI:

   abax report myproject.abax -o status.html   # HTML
   abax report myproject.abax -o status.md      # Markdown

Next steps